Ceiling texture removed from a front room before the electrician rewires
Example project
- Home
- Small 1940s stucco house in Compton with a textured ceiling and plaster walls in the front room
- Original request
- Rewire the front room and hall, with new ceiling outlets and wall switches
- Testing
- A Cal/OSHA-certified asbestos consultant samples the ceiling texture at two spots and the plaster walls at two more
- Found
- Asbestos in the ceiling texture
- Clear
- The plaster walls
- Area
- About 210 sq ft of ceiling
- Timeline
- Notice no later than 10 working days ahead, then two working days
- Cost
- $2,300
Scope of work
Four samples, the district notice, the room sealed with air filters running, the texture soaked and scraped into bags, a HEPA clean and the haul. The clearance air test, the rewiring and the new ceiling finish are separate.
Project overview
In this example, an owner in Compton is having the front room of a 1940s house rewired. The electrician needs to cut into the ceiling for new outlets, and a spray texture covers the plaster there.
The texture tests positive and the plaster walls are clear. The abatement crew takes the texture off the ceiling before the electrician starts, and the walls stay as they are.
The goal
The goal is a ceiling free of positive texture, so the rewiring starts on plaster.
Process
- First visit A Cal/OSHA-certified asbestos consultant samples the ceiling and the walls.
- Before work The abatement contractor files the district notice online and the owner empties the room.
- Day one The room is sealed, and the texture is soaked and scraped off the ceiling.
- Day two The ceiling is wiped down, the bags leave the house and an independent consultant tests the air.
Planning right
- Take the curtains and wall hangings out of the room.
- Ask the electrician to start after the air results.
- Sketch where the new outlets and switches go.
- Keep the lab report with the rewiring papers.