Example Asbestos Removal Projects in Compton

The seven example jobs below are set in Compton, East Rancho Dominguez and Bell Gardens. Each one lists what was sampled, what came out, the work days and an estimated cost.

Ceiling texture removed from a front room before the electrician rewires

Example project

Home
Small 1940s stucco house in Compton with a textured ceiling and plaster walls in the front room
Original request
Rewire the front room and hall, with new ceiling outlets and wall switches
Testing
A Cal/OSHA-certified asbestos consultant samples the ceiling texture at two spots and the plaster walls at two more
Found
Asbestos in the ceiling texture
Clear
The plaster walls
Area
About 210 sq ft of ceiling
Timeline
Notice no later than 10 working days ahead, then two working days
Cost
$2,300

Scope of work

Four samples, the district notice, the room sealed with air filters running, the texture soaked and scraped into bags, a HEPA clean and the haul. The clearance air test, the rewiring and the new ceiling finish are separate.

Project overview

In this example, an owner in Compton is having the front room of a 1940s house rewired. The electrician needs to cut into the ceiling for new outlets, and a spray texture covers the plaster there.

The texture tests positive and the plaster walls are clear. The abatement crew takes the texture off the ceiling before the electrician starts, and the walls stay as they are.

The goal

The goal is a ceiling free of positive texture, so the rewiring starts on plaster.

Process

  1. First visit A Cal/OSHA-certified asbestos consultant samples the ceiling and the walls.
  2. Before work The abatement contractor files the district notice online and the owner empties the room.
  3. Day one The room is sealed, and the texture is soaked and scraped off the ceiling.
  4. Day two The ceiling is wiped down, the bags leave the house and an independent consultant tests the air.

Planning right

  • Take the curtains and wall hangings out of the room.
  • Ask the electrician to start after the air results.
  • Sketch where the new outlets and switches go.
  • Keep the lab report with the rewiring papers.

Get a free quoteMore about popcorn ceiling removal

Kitchen ceiling and floor materials removed before a county-permitted alteration

Example project

Home
1950s house in East Rancho Dominguez, an unincorporated community, with a textured kitchen ceiling and sheet vinyl
Original request
Open up the kitchen with new cabinets and a new floor under an alteration permit
Testing
A Cal/OSHA-certified asbestos consultant samples the ceiling texture, the sheet vinyl and its backing, and the wall compound
Found
Asbestos in the ceiling texture and the vinyl backing
Clear
The wall compound
Area
About 150 sq ft of ceiling and 120 sq ft of floor
Timeline
If the address is in the district’s area, notice no later than 10 working days ahead, then three working days
Cost
$4,300

Scope of work

Samples of each material, the kitchen sealed with air filters running, the ceiling texture and the vinyl removed wet, bagging and the haul. The clearance air test, the county permit and the new cabinets and floor are separate.

Project overview

In this example, a family in East Rancho Dominguez is remodeling the kitchen of a 1950s house. The community is unincorporated, so the alteration permit comes from the county’s Public Works Building and Safety office, which asks for a notification form on alteration permits where asbestos is involved.

The ceiling texture and the vinyl backing test positive. If the address falls inside the district’s area, the district notice goes in on its own track, and the abatement crew clears the kitchen before the cabinet installer arrives.

The goal

The goal is a kitchen with the positive ceiling and floor material gone before the alteration work begins.

Process

  1. First visit A Cal/OSHA-certified asbestos consultant samples every surface the remodel will touch.
  2. Before work The owners complete the county notification form with the permit, and if the address is inside the district’s area the contractor files the district notice online.
  3. Days one to three The ceiling texture comes down wet and the vinyl is lifted and bagged, with air filters running.
  4. Last An independent consultant tests the air, then the cabinet crew starts.

Planning right

  • Ask the county counter which form goes with the alteration permit.
  • Keep the lab report with the permit papers.
  • Time the cabinet delivery for after the air results.
  • Plan where to cook while the kitchen is sealed.

Get a free quoteMore about renovation and demolition abatement

Kitchen floor layers removed from a rental bungalow before a remodel

Example project

Home
1940s rental bungalow in Bell Gardens with sheet vinyl over older tile in the kitchen
Original request
The landlord is remodeling the kitchen while the unit is empty
Testing
A Cal/OSHA-certified asbestos consultant samples the sheet vinyl, the tile under it and the mastic at three spots
Found
Asbestos in the older tile and its mastic
Clear
The sheet vinyl on top
Area
About 230 sq ft of kitchen floor
Timeline
Notice no later than 10 working days ahead, then two working days
Cost
$3,200

Scope of work

Samples of each layer, the district notice, the kitchen sealed with air filters running, both layers lifted and the mastic removed wet to the subfloor, bagging and the haul. The clearance air test and the new floor are separate.

Project overview

In this example, a landlord in Bell Gardens is remodeling the kitchen of a 1940s bungalow between tenants. Two layers of flooring cover the kitchen, and the new floor needs to sit on the subfloor.

The older tile and its mastic test positive, and the sheet vinyl on top is clear. The abatement crew removes both layers in one visit, so the cabinet installer and the flooring crew work over a clean subfloor.

The goal

The goal is a bare kitchen subfloor, so the new floor goes down with nothing positive beneath it.

Process

  1. First visit A Cal/OSHA-certified asbestos consultant samples each layer where the vinyl has lifted.
  2. Before work The abatement contractor files the district notice online.
  3. Day one The kitchen is sealed and both layers are lifted by hand.
  4. Day two The mastic comes off wet, the subfloor is cleaned and an independent consultant tests the air.

Planning right

  • Book the work for a time when the unit is empty.
  • Ask the consultant to list each layer in the report.
  • Hold the flooring order until the air results are in.

Get a free quoteMore about floor tile and mastic removal

Wrapped attic ducts removed ahead of a new air conditioning system

Example project

Home
1950s house in Compton with a furnace closet in the hall and ducts running through the attic
Original request
Add air conditioning, which means replacing the old ducts with a new set
Testing
A Cal/OSHA-certified asbestos consultant samples the wrap on the main trunk and one branch, and the tape at two joints
Found
Asbestos in the trunk wrap and the joint tape
Clear
The wrap on the branch runs
Area
About 190 ft of duct in the attic
Timeline
Notice no later than 10 working days ahead, then two working days
Cost
$4,100

Scope of work

The attic hatch and the furnace closet sealed, wet removal of the duct run into labeled bags, a cleanup and the haul. The survey, the clearance air test and the new air conditioning system are separate.

Project overview

In this example, the owner of a 1950s house in Compton is adding air conditioning. Taking out the old ducts counts as renovation under the district rule, so the survey comes before the heating and cooling crew goes into the attic.

The trunk wrap and its joint tape test positive, and the branch wrap is clear. The abatement crew takes out the whole duct run, so the new ducts go into a cleaned attic.

The goal

The goal is an attic with the old wrapped ducts gone, so the new air conditioning goes in clean.

Process

  1. First visit A Cal/OSHA-certified asbestos consultant samples the wrap and the tape from the hatch.
  2. Before work The contractor files the district notice online and the cooling crew holds its install date.
  3. Days one and two The hatch and closet are sealed, and the duct run is wetted, cut apart and bagged.
  4. Last An independent consultant tests the air, then the new system goes in.

Planning right

  • Clear the hall near the furnace closet beforehand.
  • Ask the cooling crew to start after the air test.
  • Keep the lab report with the system paperwork.

Get a free quoteMore about HVAC duct and pipe insulation removal

Small rear house cleared of positive materials before demolition for two new units

Example project

Home
Small 1950s house of about 650 sq ft at the back of a lot in Compton
Original request
Take the rear house down and build two new units on the lot
Testing
A whole-structure survey by a Cal/OSHA-certified asbestos consultant, about 14 samples from ceilings, floors, walls and the furnace closet
Found
Asbestos in the ceiling texture, the kitchen and bath floors and the wall compound
Clear
The window putty
Area
About 650 sq ft of ceiling, 260 sq ft of floor and 400 sq ft of wall
Timeline
Notice no later than 10 working days ahead, then five working days before the wrecking crew
Cost
$18,500

Scope of work

Removal of every positive material in the survey, the district notice, rooms sealed in turn, wet removal into labeled bags and the haul with its paperwork. The survey, the clearance air test, the demolition itself, the permits and the new units are separate.

Project overview

In this example, an owner in Compton is replacing a small house at the back of the lot with two new units. Demolition always needs the district notice, however small the building.

Under state law, as the district describes it, the demolition permit application also carries a copy of that notice. The survey comes first, the positive materials come out, and the wrecking crew starts afterwards.

The goal

The goal is a rear house with every positive material gone, so demolition starts when the permits allow.

Process

  1. First visit A Cal/OSHA-certified asbestos consultant samples every room and the furnace closet.
  2. Before work The contractor files the district notice online, and a copy goes to the building department with the permit application.
  3. Days one to five Room by room the ceilings, floors and wall compound come out wet and leave in sealed bags.
  4. Last An independent consultant checks the air, and the wrecking crew starts.

Planning right

  • Order the survey as soon as the two-unit plan is settled.
  • Keep the district notice and the lab report together for the permit counter.
  • Ask the wrecking crew to wait for the air results.
  • Keep the alley or side yard clear for the work truck.

Get a free quoteMore about renovation and demolition abatement

Bathroom floor with two layers sampled before the tile is replaced

Example project

Home
1950s house in Compton with a hall bathroom floor covered by two layers over the original tile
Original request
Replace the bathroom floor with new tile
Testing
A Cal/OSHA-certified asbestos consultant takes seven samples across the two top layers, the original tile, the mastic and the tub wall compound
Found
Asbestos in the original tile and its mastic
Clear
The two top layers and the wall compound
Timeline
Samples, then lab results, then a short report
Estimated testing cost
$600

Scope of work

A visit by the consultant, seven samples, a lab result for each and a short report that names every layer and where it was sampled. Removing the floor is priced on its own.

Project overview

In this example, an owner in Compton wants new tile in the hall bathroom of a 1950s house. Under the tile and a sheet of vinyl sits the original floor, and nobody knows what is in each layer.

The original tile and its mastic test positive, and the layers above them are clear. The report lists each layer, and the abatement crew is booked to remove the floor before the tile setter starts.

The goal

The goal is a clear picture of every layer, so the new tile does not sit on positive material.

Process

  1. First visit A Cal/OSHA-certified asbestos consultant cuts small samples from each layer.
  2. Results The lab reports each sample, with two positive materials and the rest clear.
  3. Next The abatement crew is booked to take the floor out.
  4. Then The tile setter schedules the new floor.

Planning right

  • Please do not scrape or sample the floor yourself.
  • Ask the consultant to mark the sample spots in the report.
  • Hold the tile order until the floor is out.
  • Keep the report with the remodel papers.

Get a free quoteMore about asbestos testing and surveys

Wall compound removed where a new electrical panel goes in

Example project

Home
1940s single-story house in Compton with a hall closet backing onto the old electrical panel
Original request
Replace the electrical panel and add circuits, which means opening the closet and hall walls
Testing
A Cal/OSHA-certified asbestos consultant samples the closet plaster and the skim coat on the hall side
Found
Asbestos in the skim coat on the hall side
Clear
The closet plaster
Area
About 60 sq ft of wall
Timeline
Less than 100 square feet of asbestos-containing material removed, so no district notice, then one working day
Cost
$1,700

Scope of work

Plastic around the hall and closet, the skim coat removed wet in a strip along the panel wall, bagging, a cleanup and the haul. The survey, the clearance air test, the electrical work and the wall patch are separate.

Project overview

In this example, a Compton owner is replacing the electrical panel of a 1940s house. The closet wall and the hall wall beside it will be opened to run new circuits.

The survey exemption for a single-unit house covers a renovation that removes less than 100 square feet of asbestos-containing material, but the owner has the walls sampled anyway. The hall skim coat tests positive, so the abatement crew removes that strip before the electrician cuts in.

The goal

The goal is a clean strip of wall, so the electrician cuts into plaster that tested clear.

Process

  1. First visit A Cal/OSHA-certified asbestos consultant samples the closet plaster and the hall wall.
  2. Results The skim coat is positive and the closet plaster is clear.
  3. Work day Plastic goes up and the skim coat strip is removed wet and bagged.
  4. Then The electrician opens the walls and sets the new panel.

Planning right

  • Move coats and shoes out of the closet first.
  • Mark the panel wall for the crew.
  • Keep the lab report with the electrical papers.
  • Plan the wall patch for after the circuits are done.

Get a free quoteMore about drywall, joint compound and plaster removal

Request a free asbestos removal quote

We recommend calling, but do feel free to contact us using this form. We'll get back to you with a free, personalized quote or additional questions as soon as possible. We're here to help.

Call (424) 373-5209

Call (424) 373-5209